Categories
News

Headhouse Crane Lift and Demo Progress

Friends,

Last Friday morning (10/10) the crews from Select Demo used a 250′ crane to lift equipment and supplies to the top of the 224′ tall Headhouse. Removal of the silver coating on the top half of the Headhouse is the last phase of cleanup at the site. All of the buildings were cleared of asbestos by late summer. The silo cleanup was completed just this past week. 

One of the fun aspects of the crane lift was the fact that it provided a great opportunity to bring down the heavy blower motor for the Civil Defense Siren. Two summers ago, we documented and removed most of the 1956 siren components so that they could be refurbished. The blower motor proved to be too heavy to safely handle in getting it down manually with ropes. The crane worked perfectly. When fully refurbished, the siren will find a new home in a community needing an emergency warning system upgrade. The young man from Jacksonville doing the work is impressive.

The viewing area near 16th St. and Phillips Ave. continues to have a lot of activity. The big crane and wrecking ball have been working to bring down the 160′ tall Turbo and Bulk Storage buildings this week. They were constructed in the early 1960’s at the south end of the AB-Mill. Ground crews with trackhoes are sorting materials from the Grocery Mix building demolition. It is fun to see the heavy equipment at work and progress being made. The best active viewing times are from 8:00 to 3:00pm Monday thru Friday.

Thanks for being a part of this important community project.

~ Team Pillsbury

Categories
News

Demo Progress – Former Employees – Date Nails

Friends,

Demolition of the 96,000 square foot Grocery Mix Building at Pillsbury continues this week. The 8000lb wrecking ball is making good progress and it is easy to imagine that the sugar tower on the roof of the building will come down this week. Yesterday the second floor forklift bridge that connected the Grocery Mix Building and the AB-Mill came down. The 6-foot shears on the trackhoe that cut the bridge were impressive to see in action!

Earlier this week we welcomed a 50-year Pillsbury employee back in Springfield as he traveled from Murfreesburo, Tennessee. He drove here to see the buildings for one last time. He worked in the Springfield plant early in his career then took the job transfer option offered in 1991 when Pillsbury sold the Springfield Plant to Cargill. He stayed on with Pillsbury for another 30-years in Murfreesboro. An extraordinary career.  We visited with several former employees in the viewing area this week. They all have great stories to tell. 

A railroad tie date nails have a date stamp and would be driven into the tie to mark the year that the tie was installed.

Railroad tie date nails became a new and interesting item for collection at the site earlier this year. In the railroad industry prior to the 1970’s, when railroad ties were replaced, a heavy nail with a date stamp would be driven into the tie to mark the year that the tie was installed. So far this year we have found tie nails with dates of: 1949, 1951, 1952, and 1958. Back in the early days of the Pillsbury plant there were 11 sets of tracks coming into the property. Many of those early railroad ties are still buried in the ground at the site.

It has been a fun and interesting week for the project. We have learned a lot about the history of the plant and the people that worked there. We have also enjoyed everyone’s commentary and speculation on how the big demolition would (or should) proceed. Please, take the time to stop by and enjoy the show as the wrecking ball continues pounding. 

Thanks for being a part of this important community project. 

~ Team Pillsbury

Categories
News

Big Demolition to Begin 10am Thursday!

Friends,

Update Wednesday, September 17:

The big crane and wrecking ball are ready to go! The smokestack comes down at 10:00am tomorrow (9/18/25).

Everyone is welcome to come and be a part of the celebration. MPF has established a great viewing area near the main Pillsbury gate. There is plenty of parking in the former employee parking lots at the corner of 15th Street and Phillips Ave.

MPF volunteers will be on site by 7am to welcome visitors. We look forward to seeing many friends throughout the day and hearing their Pillsbury stories.

Thanks for being a part of this important community project.

Update Monday, September 15:

The big crane is coming together a bit slower than originally planned. After talking to the work crew this afternoon, we are now anticipating Thursday morning before the smokestack demolition begins.

The tracks were attached to the big crane today along with the 56,000lb. counterweight. Attaching the beam sections and cables will take the entire day tomorrow and into Wednesday. Then the 5300lb. wrecking ball will be attached and we will be ready for action!

We will continue to keep everyone informed of the progress. We appreciate your patience.

The viewing area is ready and will be available all week. The former employees that stopped by today had great stories. It was the first time we had heard of poker games being played in the locker room back in the day. “I will call your two slabs of brownies and raise you a full sheet cake.” Too much fun!

Another large crane was delivered to the site late Friday. This one is an American 9299 model. A team of workers will begin assembling it on Monday. The boom on this one appears to be about 200 feet in length. Enough to reach our tallest buildings at the site.

Demolition of the 160-foot-tall smokestack is anticipated to happen on Tuesday or Wednesday to get things started. The 5-story Grocery Mix building demolition is next up after the smokestack.

Visitors are welcome to stop by to view the demolition. MPF will have a viewing area for the smokestack and Grocery Building demolition established in the Pillsbury front yard area beginning Tuesday morning. A shaded area with seating and ice water will be provided. Visitors are welcome to bring chairs as well.

There is plenty of off-street parking available in our lots at 15th St. and Phillips Ave. These are the former employee parking lots. With safety in mind, we ask that onlookers stay clear of the main gate entrance at 16th Street so that workers and equipment can access the site with minimal traffic.   

We hope to see many of our friends this week as we celebrate the bittersweet end of the Pillsbury era in Springfield.

Thanks for being a part of this important community project.

~ Team Pillsbury

Categories
News Pillsbury History

History of the Site is Now Available

Friends,

We are excited to announce that the Pillsbury Historical Context report has been finalized and is now available to read on our website. Robert and Curtis did a fantastic job bringing this together and creating such a thorough report. The interwoven details are remarkable.

The Springfield Pillsbury site represents perhaps the last large-scale remnant of mid-twentieth century manufacturing in our community. Buildings that housed Hobbs, Weaver, Allis-Chalmers, and Sangamo Electric all met their end years ago with little archived documentation.

With the Pillsbury Project, we have done our best to reasonably account for what took place within these buildings and document what that meant for the greater community. We hope you enjoy our work on this endeavor. We are grateful for the many people who have worked on the project, providing us with historical information and the many items of memorabilia. A hard copy of the report has been delivered for curation to the Lincoln Library Sangamon Valley Collection (SVC). In the coming weeks, our full set of archival photography will also be delivered and made available through the SVC.

“Pillsbury Mills in Springfield lasted only three generations. Now, as the physical plant faces demolition, the legacy of Pillsbury endures—not only in the city’s economic history but also in the lives of the employees and their families, who benefited from the health care and educational opportunities provided by the company. As people gather to share their memories, the old factory transitions from a ruin to an enduring part of Springfield’s history.”

Thanks for being a part of this important community project!

~ Team Pillsbury

Categories
News

EPA Regional Administrator Visit

Friends,

We had a visit this week from Anne Vogel, our EPA Regional Administrator. She came to see the Pillsbury site and the cleanup progress that has been made possible with over $3M in grant funding from EPA. She oversees EPA Region V which includes all of Illinois, Indiana, Ohio, Michigan, Wisconsin, and Minnesota. It was a great opportunity to demonstrate how the grant funds are being spent and why it is so important for our community.

The largest part of the cleanup at this stage of the project involves the removal of the silver paint coating on the silos and headhouse. It has approximately 5% of asbestos content and has been problematic for years. Once this 290,000 sq. ft. surface coating is removed, we can demolish these structures and recycle the estimated 70,000 tons of concrete.

These cleanup funds were a critical component in bringing the overall project together. The cleanup must be completed prior to demolition so that renewal at the site could take place. In just a few short weeks, the silo cleanup will be completed, and we can move forward to the much-anticipated large-scale demolition aspect of the project. All the smaller structures at the site have now been cleaned up and removed.

A special thank you to Frank Bowen, our volunteer Pillsbury Project photographer, for attending the site visit this week and providing great photos. He has been there for nearly all our big events and has produced an impressive photo catalog of our various site activities.

Thanks for being a part of this important community project!

~ Team Pillsbury

Categories
News

Implosion or Wrecking Ball?

Friends,

The number one question asked by community members these past few weeks is: How will the big buildings come down? Will they be imploded? Well, the answer is no. We investigated it. The cost savings were just not there, and the liability concerns were also a big factor in our decision to go with the tried-and-true methods of using a wrecking ball and hydraulic crushers. It is cost effective and much safer than using dynamite…just not quite as fast.

A big crane (an American 9260 model) was delivered to the site last week. It came on several semi-trucks and will likely be put together in the coming week. This 300,000 lb. machine should be enough to get the job done!

Cleanup contractors continue to make good progress at the site. The buildings have now been cleared of an estimated 90% of all remaining asbestos. Several of them are now fully prepared for demolition to begin. Coordination with the contractors has been excellent and we anticipate that July will be the month when the big demolition begins.

We are not certain of the building demolition sequence just yet, but we will be sure to keep everyone informed. We do know that the silos and headhouse will be the last to go. Cleanup crews are about one-third complete with the silver paint removal project prior to demolition. They will remain on-site completing this job for another two months. With the paint removed, we can then demolish the silos and recycle the estimated 70,000 tons of concrete used in their construction. A big cost savings for the overall project!

Thanks for being a part of this important community project.

~ Team Pillsbury

Categories
News

News & Updates May 2025

Friends,

Moving Pillsbury Forward continues to see good progress both at the former Pillsbury site and around the entire Pillsbury Neighborhood.

About a dozen local laborers have been working each weekday at the site preparing for and removing asbestos floor tiles in buildings these past two weeks. This work will continue for several more weeks in a systematic fashion until all buildings are cleared.

Two buildings have been fully prepared for demolition. The two-story locker room building (7300 sq. ft.) and the two-story Warehouse #1 (21,000 sq. ft.) are scheduled for demolition first. These two buildings are at the south end of the site and are anticipated to be demolished later this month.

Visitors along 15th Street this week will see workers beginning to remove the silver coating from the silos in preparation for demolition later this year. Workers will be hanging on “swing scaffolding” and using a high-pressure water misting system to remove the silver coating that was applied 60 years ago. This activity will be ongoing for about 3-4 months. Engineers have estimated that 260,000 sq. ft of coating will be removed.

MPF Volunteers have kept active in the Pillsbury Neighborhood this month. More than 12 vacant neighborhood lots have been cleared of excess vegetation, garbage, and tree branches from the June 29, 2023, derecho storm event. It has been a long recovery for this older neighborhood since that time. We are glad to have helped advance the recovery. We also edged over 800 feet of sidewalks! This was a big improvement along 15th St.

We will continue clearing lots and alleyways in the coming months. The aim is to improve the quality of life for residents of the entire neighborhood. If you would like to join us, please stop in at the 15th St. field office. We have volunteer teams working on Mondays, Wednesdays and Fridays from 8am to noon every week. We have all the tools necessary, and the work is rewarding.

Thanks for being a part of this important community project.

~ Team Pillsbury

Categories
News

It’s Happening

Friends,

Moving Pillsbury Forward has had a busy early Spring. We have contractors on site working on cleanup activities, our scheduled public meeting took place this past week, and our volunteers with Team Pillsbury have moved outside the fence line at Pillsbury.

Select Demolition crews have been on-site staging equipment and setting up for silo abatement and cleanup of buildings. A crane was utilized this past Friday to deliver equipment up to the roof of the silos. Simultaneously, other crews began the process of preparing buildings for full abatement in the coming weeks. On any given weekday, there may be more than a dozen workers on site.

The MPF public meeting at the Lanphier High School auditorium was well attended last Wednesday. Team Pillsbury volunteers placed 700 fliers throughout the neighborhoods surrounding Pillsbury and we had generous media coverage. Local citizens were able to hear about the timelines, means and methods of abatement/demolition, and ask questions. We are thankful that the overall evening program was a success. Special thanks to District #186 for hosting this event.

Team Pillsbury volunteers made the necessary switch to working outside the Pillsbury property fence line this month as we turned the site over to the contractors. Our team is now focusing on neighborhood cleanups. These past two weeks we have assisted with the cleanup of two alleyways and 6 vacant lots in the neighborhood. Good things are happening here!

Finally, neighbors have experienced a significant increase in traffic around the plant due to onlookers. We welcome visitors but ask that they remain mindful of the speed limit and stay clear of the main gate on 16th and Phillips Ave. The safety of neighbors, visitors, and workers remains a priority. We have set up a visitor viewing area on the west side of 15th St. between Enterprise and Division. Please, stop in and see us on weekdays. We have plenty of parking, seating, memorabilia, and available bricks. We are glad to have you stay for extended visits. This is a comfortable place for celebrating our rich Pillsbury history and the renewal that is taking place before our eyes.

Thanks for being a part of this important community project.

~ Team Pillsbury

Categories
News

Public Meeting April 9th, Lanphier High School

Friends,

Moving Pillsbury Forward has scheduled a Community Q&A Meeting.

Purpose: To provide an overview of the means and methods for asbestos abatement and demolition work and answer questions.

Who: Contractors, Environmental Consultants, invited guests, and YOU

When: Wednesday, April 9, 2025 / 6pm (doors open at 5:30pm)

Where: Lanphier High School Auditorium

MPF held our first public meeting at the old Lanphier High School Commons just over 5 years ago. At that time, we gathered information from the community about how best to grapple with the generational community challenge of the former Pillsbury Mills. We did a lot of listening. Then, we developed a 5-year action plan.

We are pleased to host another meeting at the new Lanphier High School Auditorium. We are glad to be in-the-neighborhood and so close to the people impacted by the site daily. A flyer is attached. Please feel free to distribute the flyer and information throughout the community. We hope to have a big gathering and a healthy discussion about the coming demolition.

Download the meeting flyer…

Thanks for being a part of this important community project.

~ Team Pillsbury

Categories
News

Pillsbury Official Demoliton Annoucement

Friends,

Moving Pillsbury Forward is pleased to announce that we have signed contracts for full cleanup and demolition of all structures at the former Pillsbury Mills site in Springfield. Yes…ALL STRUCTURES AT THE SITE WILL BE DEMOLISHED IN THE NEXT 12 MONTHS!

Select Demo Services ( https://www.selectdemo.com/ ) will begin mobilization to the site next week to begin cleanup and removal of the remaining asbestos at the site. Lead paint chip removal will also take place. These activities are anticipated to begin in April and end in early September. This aspect of the overall project has been made possible through USEPA Cleanup Grants. These grants have allowed us to develop a project design that reduces overall project costs and recycles over 70,000 tons of concrete from the 160 silos at the site.

MPF is looking forward to working with GreenTrac ( https://greentrac.us/  ) on building demolitions and site rehabilitation in the coming months. We anticipate that they will mobilize equipment to the site in late April and complete site work in March of 2026. They are an Illinois-based company that has a great track record in Springfield for working well with our local workforce. Local projects they are involved in include: the State Capitol Complex improvements, demolition of the 11th St. former Salvation Army building, and demolition of the former IEPA building at 10th St. & North Grand Ave.

Fehr Graham Engineering & Environmental ( https://www.fehrgraham.com/ ) is our firm that is responsible for overall site coordination and management services. These services include soil, water, and air sampling through the duration of the project. We (MPF) have listened to the concerns of the community and have developed a rigorous perimeter and site safety monitoring protocol.

 A designated demolition viewing area along 15th St. has been set up at the former Pillsbury employee parking lot east of 15th St between Enterprise St. and Division St. MPF volunteers have a field office set up in a 40ft shipping container. Seating, shade canopies, and bottled water will be available most weekdays. We hope to make this an inviting community gathering place and honor the rich history of the site while also looking forward to renewal for the community.

MPF has begun to plan for a public meeting to engage questions and comments from the community about the overall Pillsbury Project. We anticipate an announcement in the coming days as we firm up a date, time, and location.

Yes…It has been a long time in coming! An incredible community effort has finally made it happen! Thank you for being a part of this important community project.

~ Team Pillsbury